Recent Projects
Significant recent alternative & renewable energy assignments include the following:
| Goldwind USA |
|---|
|
Sargent & Lundy performed engineering for Goldwind’s Shady Oaks 109.5 MW Wind Farm Project, which includes 68 1.5-MW and 3 2.5-MW Goldwind permanent magnet direct drive (PMDD) turbines. The project is located in Lee County in north central Illinois. Our scope of work included engineering and design of a 138-kV Interconnection Switchyard and a 138/34.5-kV Project Substation, coordination with ComEd and PJM for interconnection to the 138-kV transmission system. In addition, we are providing both on-site quality control surveillance for the substation construction and commissioning services. The project is scheduled to be in service by the end of 2011. Project Profile: Shady Oaks Wind Farm |
| BP Wind Energy |
|
Sargent & Lundy performed engineering for the Trinity Hills Wind Farm project and the Sherbino Mesa II Wind Farm project, both located in Texas. Sargent & Lundy's scope for the 225-MW Trinity Hills project included the engineering and design of a 345/34.5 kV substation, the 34.5 kV underground collection system, and 3.5 miles of 345-kV transmission line. Our scope for 150-MW Sherbino Mesa II included the engineering and design of the 138/34.5 kV project substation, 138 kV junction switchyard, 34.5 kV overhead and underground collection system, and 10 miles of 138 kV transmission line. Engineering was initiated in August 2010 on Trinity Hills and October 2010 on Sherbino Mesa II. Engineering drawings for both projects were issued for construction in March 2011. Project Profile: Trinity Hills and Sherbino Mesa II Wind Farm Projects |
| Horizon Wind Energy |
| Twin Groves Wind Farm |
|
Sargent & Lundy performed engineering for the interconnection of the Horizon Wind Energy Twin Groves Wind Farm to the Commonwealth Edison transmission network. Our engineering and design included the 34.5/345 kV substation at the termination of the wind generator collection system, 16 miles of 345-kV transmission line, a 345 kV substation, a 3-breaker ring bus adjacent to the existing transmission line, and coordinating the interface of the protection and control systems. The project was constructed in two phases, each generating 200 MW of power. Phase II was completed at the end of 2007. The facility includes 267 wind turbine generators, with a rated capacity of 1.5-1.65 megawatts each. Project Profile: Twin Groves Wind Farm InterconnectionWork has continued with Horizon Wind Energy for the interconnection of additional wind farms to various transmission networks. Services provided by Sargent & include transmission line and substation engineering & design, collection system engineering & design, material and equipment procurement support, and construction field services. Project Profile: Pioneer Prairie Wind Farm InterconnectionProject Profile: Meadow Lake Wind Farm Interconnection Project Profile: Top Crop Wind Farm Interconnection |
| Wind Farm Grid Interconnection |
|
Sargent & Lundy has performed engineering for the interconnection of wind farms developed by Acciona and Iberdrola to the Commonwealth Edison transmission grid. Our scope of work included detailed engineering for 345-kV and 138-kV switchyards. Both of these projects were placed in service in 2009. Sargent & Lundy has also been providing support to BP Wind, Gestamp, and other wind energy developers with technical support for proposed transmission interconnections. Our services have included power system impact studies, preparation of interconnection applications, and interface with ISO representatives. Project Profile: Twin Groves Wind Farm Interconnection |
| Wind Turbine Foundation Assessments |
| We performed several recent independent assessments of wind turbine foundations on several projects for a wide range of wind turbine manufacturers. The scope included independent 3rd party foundation analysis and design, including evaluation of the dynamic rotational stiffness relative to wind turbine manufacturer requirements, and an overall evaluation of foundation designs and construction plans. |
| Assessment of Renewable Alternatives |
| For a regional utility, we performed a technology survey and analysis investigation of commercially available renewable energy technologies including wind power, biomass thermal, geothermal, solar thermal, and solar photovoltaic technologies. |
| Global Solar Technologies Assessment |
| Working for the U.S. Department of Energy (DOE/EERE) and in close collaboration with the National Research Council, we performed a comprehensive review and update of the global development of solar power technologies. The resulting report is widely referenced in the industry and is available from the National Renewable Energy Laboratory's Web site. |
| Hydroelectric Development, Design, and Commissioning |
| Our hydroelectric generation assignments in the past decade have included every aspect of development, financing, siting, design, construction, commissioning, operation, and asset transfer for owners, lenders, and developers. |
| Integrated Solar /Combined-Cycle Plant Feasibility |
| Working for the World Bank, we assessed the feasibility of an integrated solar combined cycle plant (ISCC). Our scope included technical and contractual reviews, as well as a review of the integration between the solar and combined cycle islands. |
| Landfill Gas Evaluation |
| We have provided evaluations of alternate uses of landfill gas, such as for power generation or conversion to pipeline gas. |
| Landfill Gas Facilities Detailed Design |
| For a utility client, we developed the detailed design and arrangement of balance-of-plant (ex-gas turbine) for a series of landfill gas facilities, including landfill gas (LFG) piping, conditioning and compression, and all services and structures. The power block for these projects consists of a single 5-MW solar gas turbine designed specifically for LFG applications. |
| Repowering for Burning Multiple Refuse Fuel Burning |
| Sargent & Lundy provided the engineering and design to support repowering of older three units for alternative fuel firing. The existing steam turbines remain intact, while the existing steam generators were retired, replaced with a single circulating fluidized steam generator capable of burning coal refuse, petroleum coke, wood refuse, and tire-derived fuel. |
| Site and Technology Screening for Firing Waste Wood & Coal |
| For a utility client, we conducted a siting and technology screening study for the use of wood waste. The screening study evaluated the best locations on the transmission system and identified the generation technology and capacity options to be used as the basis for the site evaluations and in developing the conceptual designs and cost estimates. Options centered on steam generating units capable of burning a mix of wood waste and Powder River Basin coal. |









