Recent Substation Projects
| Air Liquide |
|---|
| Sargent & Lundy served as owner's engineer to Air Liquide for two substation projects-the Geismar 138-kV Substation in Louisiana and the Scotford 138-kV Substation in Saskatchewan, Canada. Our team developed the EPC specification for the Geismar Substation and evaluated the bids for the Geismar and Scotford Substations. Completed in 1999. |
| American Transmission Company |
| Central Portfolio |
| As part of an EPC project team led by Kenny Construction Company, Sargent & Lundy is performing engineering for a group of 345-kV and 115-kV substations located in the Wausau, WI area. Many of the projects are associated with the addition of 500 MW of generation at the Weston Generating Station, scheduled to come on line in 2008. Sargent & Lundy's scope of work includes support for Public Service Commission and Department of Natural Resources permits, as well as design of new and upgraded facilities. |
| East Portfolio |
| Sargent & Lundy was selected by ATC as the engineering firm for their East Portfolio, which includes Milwaukee and the southeastern region of Wisconsin. The work includes a broad range of services for new and upgraded 69-kV and 138-kV substations. S&L is also performing construction coordination, quality control surveillance and commissioning services for a number of ATC projects. |
| Calpine Riverside Generating Station Interconnection |
| Sargent & Lundy performed complete engineering and design for the interconnection of an independent power project generating station to the American Transmission Company system as part of an EPC team. This included a 138-kV switchyard and transmission tie line. Our scope of work included electrical testing and commissioning services. Sargent & Lundy was the engineering subcontractor to M. J. Electric of Iron Mountain, MI for this EPC contract. The project was completed in 2003. |
| Baltimore Gas & Electric |
| Sargent & Lundy is performing engineering for BG&E under a general services agreement. Recent projects have involved the addition of capacitor banks, upgrades to protection and control systems and other modifications to existing substations. |
| Calpine Corporation |
| Magic Valley |
| Sargent & Lundy was the engineer for the new 138 kV Magic Valley Switchyard in Texas and the Magic Valley power plant. This switchyard was constructed as part of the independent power project generating station for interconnection to the existing utility system. This work was performed under an EPC contract with Zachry Construction Corporation and was completed in 2000. |
| Pine Bluff |
| Under a joint venture with Zachry Construction Company, Sargent & Lundy performed the engineering and procurement activities for the Pine Bluff Power Plant and 115 kV switchyard. The switchyard interconnects the generating station project to the existing utility system in Arkansas. This project was completed in 2000. |
| City of Anaheim Public Utilities Department |
| Sargent & Lundy is supporting the City of Anaheim, CA in a major upgrade/expansion of its transmission and distribution system. Sargent & Lundy is serving as owners engineer and construction manager for a series of gas-insulated substation (GIS) projects located in both enclosed and outdoor facilities. These projects include the following: |
| Park Substation |
69 kV/23.8 kV indoor/underground GIS, placed in-service in 2006. Project Profile: Park Substation Project |
| Lewis - Vermont Project |
| 230kV/34kV GIS in an open-air substation and a 230-kV transmission line, scheduled to be completed Fall 2007. |
| Anaheim Substation |
| 69 kV/13.8 kV indoor GIS located in downtown Anaheim, scheduled to be completed Spring 2008. |
| City of Tallahassee |
| To accommodate the addition of a new unit at the Hopkins Generating Station, S&L is designing an expansion of the Hopkins 115-kV switchyard. Completed in 2005. |
| City Public Service of San Antonio |
| As Owner's Engineer for the Hamilton Wolfe and Toyota 138-kV Substations, S&L developed specification packages to obtain EPC bids, performed technical bid evaluations and performed technical reviews of engineering deliverables. These projects were completed in 2004. |
| Conectiv |
| Under a long-term services agreement, S&L has been performing engineering for a variety of substation modifications. Recent projects have included circuit breaker replacements, RTU additions, addition of a 69-kV line terminal, 69-kV capacitor bank additions, and upgrades for increased ampacity ratings. |
| Constellation Power |
| Sargent & Lundy performed engineering and design for three switchyards for Constellation Power independent power project generating stations. These are the University Park 138 kV switchyard in Illinois, the Hansom Lake 345 kV switchyard in Pennsylvania and the Wolf Hills 138 kV switchyard in Virginia. Completed in 2001. |
| Dairyland Power Cooperative |
| Sargent & Lundy performed engineering and design of Dairyland's substation expansion project to accommodate two new generating units to be installed north of the existing Elk Mound substation. Sargent & Lundy's work encompassed the physical design associated with expansion of the 15 kV and 161 kV sections of the substation. This included foundation design, development of drawings for new structures and equipment, grounding design, below grade conduit and cable trench layout, design and drawings for 15 kV and 161 kV buswork and design of shielding for lightning protection. Completed in 2001. |
| Duke Energy |
| S&L worked with Duke Energy to develop standards for substation design and standard specifications for substation equipment. The first phase of this project included a review of Duke's existing standards and development of a list of the necessary revisions and additions. Phase II of the project involved the development of the sections of the standards manual and technical specifications that were Duke's highest priority. The objective of this project was to prepare a complete standard substation design manual and a set of specifications for all major substation equipment. Phase II of the work was completed in 2000. |
| Enron (NEPCO) |
| Combustion turbine peaking unit generating stations were constructed by ENRON at two sites in Tennessee and one in Mississippi that were interconnected to the Tennessee Valley Authority (TVA) 500-kV transmission grid. Sargent & Lundy was selected to provide engineering for the new substations at these generating stations. Our team worked with National Energy Production Corporation (NEPCO), an Enron Company, and T&D Engineering and Construction (TDEC), a subsidiary of Enron, to complete the design of these 500-kV substations on a fast-track schedule. These projects were completed in 1999. |
| Exelon |
| ComEd |
Working together with Exelon's Contractor of Choice (COC) teams that are led by Kenny Construction Company and Infrasource, S&L is performing engineering for a number of 138-kV and 345-kV substations throughout northern Illinois. In addition to engineering, S&L coordinates the electrical testing and commissioning of each substation and performs construction quality control services. As Exelon's Engineer of Choice, S&L is coordinating nuclear plant switchyard modifications during refueling outages. In addition, S&L and the COC team has been working on a series of major, enclosed substation projects for the ComEd in Chicago's central business district. Project Profile: Chicago Optimization ProjectsProject Profile: Madison and Ohio Substation Projects |
| SCADA Installation Programs |
| Sargent & Lundy performed engineering and design for the installation of SCADA (supervisory control and data acquisition) programmable logic controllers (PLCs) or remote terminal units (RTUs) at over 60 existing substations throughout the ComEd service territory in northern Illinois. The SCADA systems allow ComEd to improve the reliability of the transmission and distribution system and respond more quickly and efficiently to system abnormalities. This work was performed under an EPC contract. M. J. Electric of Iron Mountain, MI was the prime contractor and Sargent & Lundy was the engineering subcontractor. Our scope of work as the engineer on the EPC team included development of SCADA point lists; SCADA system engineering and design, including transformer LTC control, regulation, and tap position monitoring; schematic, wiring diagrams, and demolition drawings, preparation of material lists; and design and specification of associated equipment such as auxiliary relays, cables, conduits, and cable trays. Completed in 2001. |
| PECO |
| Working directly as an Exelon Engineer of Choice and as part of the Infrasource Contractor of Choice team, Sargent & Lundy is designing 138-kV and 230-kV substation modifications. These projects involve the addition of line terminals, circuit breaker replacements, and relay upgrades. |
| Horizon Wind Energy |
| Twin Groves Wind Farm |
|
Sargent & Lundy performed engineering for the interconnection of the Horizon Wind Energy Twin Groves Wind Farm to the Commonwealth Edison transmission network. Our engineering and design included the 34.5/345 kV substation at the termination of the wind generator collection system, 16 miles of 345-kV transmission line, a 345 kV substation, a 3-breaker ring bus adjacent to the existing transmission line, and coordinating the interface of the protection and control systems. The project was constructed in two phases, each generating 200 MW of power. Phase II was completed at the end of 2007. The facility includes 267 wind turbine generators, with a rated capacity of 1.5-1.65 megawatts each. Project Profile: Twin Groves Wind Farm Interconnection |
| Jacksonville Electric Authority |
| Brandy Branch and Normandy Substations |
Sargent & Lundy engineered the expansion of these 230-kV substations to accommodate the addition of new 230-kV line terminals. This project was completed in 2005. T&D Maintenance Practices Review - To improve system reliability, Jacksonville Electric Authority (JEA) requested a review of their T&D maintenance practices and provide recommendations for cost-effective methods of monitoring and maintaining substation equipment. Sargent & Lundy was also requested to evaluate the JEA system to determine the causes of an unacceptably high level of equipment failures. These studies were completed in 1998. |
| Louisville Gas & Electric |
|
Sargent & Lundy is performing complete project services for this downtown 138/13.8-kV substation including related underground and overhead transmission lines. An existing open-air substation is being demolished and replaced by a multilevel, enclosed GIS facility with a cable vault area housing 138-kV transmission lines and 15-kV distribution feeders. The project includes reconductoring a 69-kV underground line and replacing four 138-kV oil-filled underground transmission cables with XLPE cable and high-pressure gas-filled cable. Our scope includes overall program management, engineering and design, procurement support, construction management, and commissioning. Engineering was initiated in September 2006, and the substation is scheduled to be energized mid-2008. Project Profile: Waterside West 138/13.8 kV Project |
| Lower Colorado River Authority |
| The Hays Energy 345 kV switchyard and the Zorn 345 kV substation expansion were designed by Sargent & Lundy for the Lower Colorado River Authority, Austin, TX. Sargent & Lundy's scope of work included complete physical design and development of schematics and wiring design. These projects were completed in 2000. |
| Nevada Power Company |
|
Sargent & Lundy is providing engineering for this 138/12-kV substation adjacent to the Las Vegas resort "Strip" and designing the associated overhead and underground transmission and distribution lines. Segments of the 5 miles of line are being designed to accommodate a future, overbuilt 230-kV circuit and the 138-kV circuit and future 230-kV circuit to be installed underground. Engineering was initiated in August 2007 and the project is planned to be in service by June 2009. Sargent & Lundy's team includes Arcadis, Finley Engineering, and USi/GAI. Project Profile: Collman 138/12 kV Project |
| New York Power Authority |
Connecting 11 Peaker Plants at 7 New York City Sites Project Profile: In-City Generation Project |
| PacifiCorp |
| Wasatch Front Quantum Leap Projects |
|
As part of an EPC team, Sargent & Lundy is performing complete engineering for a major upgrade of the transmission and distribution system in the PacifiCorp Salt Lake City region. The prime contractor is Kenny Construction Company of Chicago, IL. The scope of work includes 12 new 138/12.5-kV substations and upgrades of 19 existing substations. In addition to engineering, Sargent & Lundy's scope of work includes construction quality assurance and testing and commissioning services. The majority of the projects were completed to meet summer peak loads in 2003 and 2004, and the remaining projects were completed in 2005. Profile: Quantum Leap |
| Substation Engineering Services |
| Sargent & Lundy is performing engineering for new substations and modifications to existing substations throughout PacifiCorp's service territory under a professional services agreement that was awarded to S&L in 2004. |
| Reliant Energy |
In association with the design of the new El Dorado generating station south of Boulder City, Nevada, Sargent & Lundy designed the 230-kV substation. The scope of our work as the engineer for this EPC contract included the complete design of a three-bay 230-kV breaker-and-a-half arrangement, specifying all equipment and providing technical interface with the connected utilities. This substation provided connections for three generating units for a total of 700 MW, with three outgoing lines to two different utilities. This project was completed in 1999. Other work for Reliant Energy independent power projects include the Aurora 345/138 kV substation in Illinois as the engineer in the project joint venture organization and the Equistar 345/138 kV substation in Texas as the engineer in the project joint venture organization. These projects were completed in 2000. |
| Rochelle Municipal Utilities |
| To provide electric service to a new ethanol manufacturing plant in central Illinois, Sargent & Lundy was retained to engineer the Caron Road 138-kV Substation. Completed in 2006. |
| Salt River Project |
|
We performed engineering and design services for the Hassayampa 500 kV Switchyard project. In response to requests for both transmission and generation interconnections to the Palo Verde hub by various utilities, energy service providers and other interests, a new satellite switchyard was constructed near the existing Palo Verde Nuclear Power Plant. This new 500 kV breaker-and-a-half switchyard has an ultimate arrangement of 10 bays, with 20 positions available for the termination of transmission lines and generating station tie lines. Completed in 2003. Profile: 500-kV Hassayampa Switchyard - Supporting New IPP Generating Plants |
| San Diego Gas & Electric Company |
Sargent & Lundy is leading a team that is providing a wide range of services to support SDG&E on their proposed major, new transmission interconnection from the east side of their service territory - the Sunrise Powerlink. The project is proposed to include approximately 100 miles of new 500-kV transmission line, approximately 30 miles of new 230-kV line, a new 500/230-kV substation, and upgrades to a number of existing lines and substations. The scope of work is divided into three phases: I - Route evaluations, public outreach, environmental licensing, and preliminary engineering: II - Detailed engineering, procurement support, and land acquisition support, and III - Construction management. The current plan is to file the environmental permit applications in 2006, start construction in the 3rd quarter of 2008, and place the line in-service in 2010. Project Profile: Sunrise Powerlink |
| Southern California Edison |
| SCE awarded an engineering services agreement for substation projects to S&L in 2004. Current assignments include capacitor bank additions, circuit breaker replacements and other equipment upgrades at existing 69/12-kV substations. |
| Tennessee Valley Authority |
Sargent & Lundy performs a substantial amount of engineering for the TVA transmission system. TVA has awarded long-term engineering alliance contracts to S&L on the basis of comprehensive technical and commercial evaluation processes that have provided the basis for a continuous working relationship. The current contract extends to mid-2009, with options to extend for five additional years. Projects have included new 230/115-kV substations, 161-kV switchyards and 500-kV switchyards for the interconnection of independent power project generating stations. They have also included upgrades to existing substations, addition of capacitor banks, relay system upgrades, replacement of obsolete circuit breakers, and installation of SCADA systems. Project Profile: TVA |
For more information, contact:
Tom Eisenbart, Senior Vice President
Tel: 312-269-6478
E-mail: thomas.r.eisenbart@sargentlundy.com
Frank Shainauskas, Manager
Tel: 312-269-7654
E-mail: frank.c.shainauskas@sargentlundy.com









